Invitation to bid

Project:
Development of Upper Floors of The Anglers Rest

Bid due date:
12 noon on Saturday 7 March 2020

Project description:

Package 1:
Restructuring of the rear entrance to the 1st floor as described in the Scope of Works in drawing 1 below.

Package 2:
Refurbishment of the attic accommodation as described in drawing 2 below.

Submission of bids:
Bids should be submitted to David Allwood, Director of Bamford Community Society (BCS) responsible for Buildings Development, either in hard copy to: The Anglers Rest, Main Road, Bamford, Derbyshire  S33 0DY or electronically to david.anglersrest@yahoo.com .

Approximate start date:
The work is expected to start in May and be completed before the end of June 2020 although the actual start date is dependent on when full funding is secured.

Bid instructions:
Pricing to be provided for each package and subdivided between civil, electrical and plumbing trades. The successful bidder is required to supply all materials except those identified below.

Package 1 price to be subdivided between the doorway/landing work and the staircase/wc work. A handbasin & wc will be supplied by Bamford Community Society.

Package 2 price to be subdivided between: installation of steel purlin; installation of Velux windows; construction of stud walls and lining of exterior walls including installation of firedoors & frames; shower room (a handbasin and wc will be supplied by Bamford Community Society); heating and hot water systems (the drawing shows the use of electric storage heaters but the bidder should also provide a price for a gas-fired heating & hot water system).

Further information:
For further information, clarifications and arrangements for a site visit contact David Allwood (david.anglersrest@yahoo.com)

17 February 2020
Bamford Community Society The Anglers Rest, Main Road, Bamford, Derbyshire  S33 0DY